CROMWELL — In just one short month, the focus of the Turkey Creek Regional Sewer District board has shifted dramatically.
Read MoreCROMWELL — In just one short month, the focus of the Turkey Creek Regional Sewer District board has shifted dramatically.
Read MoreNORTH WEBSTER — Lakeland Regional Sewer District is one month closer to having the $29M sewer project in the books after meeting Thursday evening, April 6, at the North Webster Community Center.
Read MoreCROMWELL — As Turkey Creek Regional Sewer District wraps up one multi-million dollar project, the board members seemed surprised to find themselves gearing up for yet another one. After several months of attempting to address grievances with bills coming from the town of Syracuse, TCRSD passed a motion to begin a $53,000 study that will help the board determine the process on becoming self-sufficient.
Read MoreCROMWELL — The sheer lack of public members present during the sewer meeting Monday, Feb. 20, stands as testament to the successful sewer project by Turkey Creek Regional Sewer District as it nears completion. Board members and engineers announced proudly the final stages of the S.W.A.P project wrapping around the local lakes.
Read MoreNORTH WEBSTER — Thanks to the work of numerous contractors, board members, DLZ project engineers and local homeowners, Lakeland Regional Sewer District is expecting to complete the $29 million sewer project just $15,000 over budget, a .07 percent change.
Read MoreCROMWELL — Board members of the Turkey Creek Regional Sewer District met to discuss a few important decisions Monday evening, Jan. 16. The board opened the meeting by welcoming existing board member Jim Boone as the new board vice president.
Read MoreNORTH WEBSTER — The Lakeland Regional Sewer District met at their standard location Thursday evening, Jan. 5. Although the North Webster Community Center is the current host of the 6 p.m. monthly meeting, board members anticipate being able to meet in one of the rooms of the brand … Read More
SYRACUSE — The mood at the December meeting of Turkey Creek Regional Sewer District turned quickly from jolly to pensive as the board moved from Christmas party mode to discussions of a $53,000 study during the Monday, Dec. 19, meeting.
Read MoreNORTH WEBSTER — The board members of Lakeland Regional Sewer District heard positive project updates on Thursday evening, Dec. 1, while also debating on approving a request to extend one contracted amount. During the regular monthly meeting held at the North Webster Community Center, the board kicked off … Read More
CROMWELL — With updated facilities and services come updated expenses, at least when it comes to insuring those new and updated assets, Turkey Creek Regional Sewer District focused on changing costs during its regular monthly meeting Monday evening, Nov. 21.
Read MoreNORTH WEBSTER — Lakeland Regional Sewer District board members met Thursday evening, Nov. 3, to discuss project updates and setbacks. After hearing updates from DLZ engineer Casey Erwin, it seems the project is nearing completion, shining a light through the very long tunnel of a project. Of the … Read More
CROMWELL — Turkey Creek Regional Sewer District trustees met for a brief regular monthly meeting Monday evening, Oct. 17. The board heard updates on the sewer project wrapping around the Wawasee area from engineer Brian Houghton, who provided info about each of the complete or nearly complete contracted areas.
Read MoreNORTH WEBSTER — Change orders and construction progress were the talk of the evening for the Lakeland Regional Sewer District board during the regular monthly meeting held at the North Webster Community Center.
Read MoreSYRACUSE — Turkey Creek Regional Sewer District held an unusually brief monthly meeting on Monday, Aug. 15. Though no public members were present, the board was thrilled to hear that the large S.W.A.P (South Shore-Waco Drive Area Project) continues to run smoothly and all items are on or ahead … Read More
NORTH WEBSTER — The four contracted areas of the projects are quickly approaching the substantial completion date of Dec. 27, with final touches being added to each area. Contract A, bid by Selge Construction, covers Shoe Lake, Irish Lake, Sawmill Lake and part of Sechrist and Barbee lakes. Casey Erwin, DLZ project engineer, estimated this area to be 59 percent complete with the majority of laterals installed and grinder stations being placed, as well.
Read MoreSYRACUSE — The Turkey Creek Regional Sewer District met Monday evening, July 18, to handle monthly business and approve the adoption of the 2016 sewer use ordinance. The board discussed the month’s claims, approving the payment of each one other than the monthly bill to the Syracuse town. … Read More